Bond reduction
Case Study - Section 38 Estate Completion
How JLES took on the outstanding highway and sewer works at Court Street, Woodville, on a 100% fixed fee.

A live residential development taken from unfinished roads to a completed highway and sewer scheme.
ÂŁ156k+
Bond reduction
6 months
Project duration
0 extras
100% fixed fee
40+
Resident liaisons
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Carriageway Resurfacing
Client: Morro Partnerships
Court Street, Woodville · Section 38 adoption
The unfinished estate was frustrating residents, with sections of carriageway and footway still to be completed. Outstanding highway and sewer issues had to be identified and resolved to the standards required by the adoption authorities.
With only one access point, the works had to be carefully sequenced in a live residential environment, including the heavy-duty binder course and final Superflex surface course, while 76 residents kept access to their homes.
Morro Partnerships now has a completed estate that can progress to adoption, with the outstanding highway and sewer bonds reduced to zero. JLES delivered the project on schedule, coordinating every remedial workstream through to completion on a 100% fixed fee, with residents given advance notice of key works and surfacing dates.
Sewer and manhole remedials
Manhole chambers reconstructed from the cover slab, damaged cover slabs replaced and all manholes raised to finished levels. Lifting eyes sealed, water ingress and water holding resolved, and damaged pipes replaced through excavations up to 2m deep.
Gully and ironwork remedials
Extensive gully works, including excavations to address Y-junctions, missing gullies and damaged pipes, plus all highway ironwork raised to level.
Binder and surface courses
3,300m² of heavy-duty carriageway binder course and 1,175m² of footway binder course, finished with 2,850m² of Superflex surface course and 1,165m² of footway surface course.
Block paving and crossings
450m² of block paving, including block-paved speed tables, plus tactile crossings, newly constructed footways and a private driveway.
Highway and sewer works delivered in stages, with final remedials completed before progressing to adoption.