Case Study - Section 38 Legacy Adoption

East Witchel: ÂŁ106.6k bond reduction on a 100% fixed fee

How JLES South West finalised the outstanding Section 38 agreement at East Witchel, Swindon as specialist contractor for David Wilson Homes, on a 100% fixed fee.

A large, multiphase residential development taken from outstanding adoption issues to a completed scheme.

ÂŁ156k+

Bond reduction

6 months

Project duration

0 extras

100% fixed fee

40+

Resident liaisons

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

Carriageway Resurfacing

Client: David Wilson Homes

East Witchel, Swindon · Swindon Borough Council

The challenge

During the onsite works, an additional 360m² of carriageway surfacing was found to be required that had not been originally accounted for. The segment was particularly difficult, needing extensive level surveys, and was undertaken at no extra cost to the client. Continual level checks and kerb face deviations prevented water accumulating.

An engineer monitored the tarmac laying and agreed deviations with the adopting authority, so the works met Swindon Borough Council’s expectations and no further visits disrupted residents. Residents were also engaged throughout.

The outcome

David Wilson Homes appointed JLES South West as main contractor to finalise the Section 38 works. Our Adoption Management System progressed the agreement to completion, facilitating an immediate cancellation of the bond, with the works accepted without further carriageway inspections and no additional charges to the client.

What we delivered

Carriageway surfacing

An additional 360m² of surfacing delivered at no extra cost, backed by level surveys, continual level checks and kerb face deviations to prevent holding water.

Block paving relay

110m² of block paving relaid around the development, including resetting utility covers, replacing water boxes and replacing street name plates on residents’ fences.

Block paviour jet cleansing

All block paviours jet cleansed, keeping sand from standard areas off the permeable paviours so their drainage capability was protected.

Highway improvements

Delivered as part of a comprehensive estate completion package, including cutting back large trees overhanging the adoptable highway.

See the difference

Road after the works Road before the works

Collaboration with Swindon Borough Council meant the works were accepted without further carriageway inspections.