Case Study - Section 38 & 104 Adoption

Harron Homes: ÂŁ156,000+ bond reduction and adoption secured in 6 months

How JLES Northern finished the outstanding S38 & S104 agreements at High Banks, Silsden, on a fixed fee basis with zero extras.

The finished High Banks road network, adopted-standard surfacing throughout, with residents in their homes the whole time.

ÂŁ156k+

Bond reduction

6 months

Project duration

0 extras

100% fixed fee

40+

Resident liaisons

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

Carriageway Resurfacing

Client: Harron Homes

High Banks, Silsden · Bradford Metropolitan Borough Council and Yorkshire Water adoption

The challenge

Harron Homes needed the outstanding S104 and S38 agreements finished on an occupied estate. That meant sewer repairs up to 6 metres deep, road closures and temporary driveway restrictions for a large number of residents.

Adverse weather added pressure to a programme that had to end with sign-off from both Bradford Council and Yorkshire Water.

The outcome

JLES secured the maintenance certificate from Bradford Metropolitan Borough Council and Yorkshire Water, releasing ÂŁ156,000+ of bond for Harron Homes. The project finished within 6 months on a 100% fixed fee, with no extra charges to the client.

What we delivered

6-metre deep excavations

to replace faulty drainage sections, planned and shored for safety and structural integrity.

Manhole and kerb repairs

including replacement chamber rings and damaged covers, with kerbs realigned across the entire site.

Complete final surfacing package

to bring the highways up to adoptable standards.

A resident liaison plan

with constant communication, plus traffic and pedestrian management to keep disruption low.

See the difference

Road after the works Road before the works

From patched, worn surfacing to a fully resurfaced, adoption-ready road, delivered alongside 6-metre drainage repairs.