Peugeot Works, Coventry

PROJECT OVERVIEW

Peugeot Works is a collection of brand-new homes constructed by our long-standing clients Taylor Wimpey. JLES were awarded the project on a consult and construct basis working as; Main Contractor, Managing Agent & Technical Consultant.

The highways & sewers on this project were built over a period of 10 years by various groundworks contractors. When Taylor Wimpey appointed JLES, the development had been subject to a lot of general wear & tear, and these aspects required extensive remedial works carrying out before all roads and footways could be final surfaced.

THE SCHEME INVOLVED

• Five phases of remedial and final surfacing works.

• Street lighting restorative works.

• Sewer cross-connections.

• All sewer works and network concluded and adopted immediately.

• Legal works & planning amendments.

• JLES legal team implemented short form Section 38 agreements.

• Installation of block paved focal squares.

• Associated tree planting throughout the entire scheme.

KEY FEATURES

• Lump sum, fixed cost contract to secure S104/185 sewer adoption.

• Lump sum, fixed cost contract to secure highways sign-off on a ‘phase by phase’ basis.

• Works invoiced upon Local Authorities written acceptance.

• Resident liaison and customer care package.

• Consultancy and technical support work to satisfy Severn Trent Water & Coventry City Council design requirements.

CHALLENGES

Due to the length of the build programme, the early phases of this development had been subjected to a decade of wear and tear which resulted in large areas of the footways and road being re-constructed in entirety.

The Section 38 Agreements had not been executed and significant inconsistencies existed between the designs and the as-constructed infrastructure.

BEFORE & AFTER

PROJECT Statistics

100

%

fixed Fee

£

1,200,000

Contract Value

Extras Charged

400

+

Resident Liaisons

%

Reduction on internal resource

12

Months Project Duration
Weeks Project Duration

Carriageway Resurfacing
Weeks Project Duration

£

Bond Reduction

%

Resident Satisfaction
Jon Hearn
Engineering Manager
0330 165 7902
central@jlesgroup.com
100

Fixed Value

1,200,000

Contract Value

Extras Charged

400

Resident Liaisons

reduction on internal resource

12

month project duration

bond reduction

Resident satisfaction

100

%

Fixed fee

Extras charged

£

Bond reduction

400

+

Resident liaisons

%

Reduction on internal resource

12

Month project duration

£

1,200,000

Contract value

%

Resident Satisfaction

Client feedback

“We appointed JLES as our Contractor/ Consultant to undertake the Estate Completion Works on our development in Coventry. They facilitated the immediate adoption of the sewer network throughout the entire scheme and have completed the remedial works and final surfacing to 4 phases of the project, achieving sign-off by Coventry City Council. All works were completed on programme and with very little resource expended by Taylor Wimpey, resulting with the scheme being placed onto its maintenance period. We are looking forward to them concluding the remaining phases and achieving final adoption of the scheme in the near future”

Technical Director | Taylor Wimpey

other Projects

By clicking “Accept”, you agree to the storing of cookies on your device to enhance site navigation, analyze site usage, and assist in our marketing efforts. View our Privacy Policy for more information.