West View, Creech St Michael

PROJECT OVERVIEW

This complex S278 scheme had many restrictive measures in place & required a large scope of high remedial works in order to get the maintenance certificate released. This involved: 

• Kerb repairs and replacements throughout the development

• Approximately 325M2 of full highway & footpath re-surfacing

• Drainage dig-downs to multiple manholes

• Full resurfacing of traffic calming tabletop to be able to achieve adequate vertical deflection on ramps

• Raising of iron works, gully relocation, gully connection remedials and cleansing

• General site maintenance



CHALLENGES

As well as being located adjacent to a pre-school, this development has only 1 access and egress point and a heavy flow of traffic on the trunk road, therefore the scheme involved:

• Heavily involved health & safety coordinators to ensure all required safety measures where in place

• Due to the location of the junction, extensive traffic management was required to ensure access was available whenever necessary

KEY FEATURES

• JLES Exeter were appointed as the Specialist Contractor on this complex S278 legacy scheme. to acquire the maintenance certificate for their client, David Wilson

• Lump sum, fixed cost to complete S278 works and achieve maintenance

• Works invoiced upon Local Authority written acceptance

• Supervision and management of works throughout

• Consultancy and technical work to satisfy outstanding adoption documentation

• JLES acting as Principal Contractor, Main Contractor & the developers Managing Agent

• Resident liaison & full customer care package

PROJECT Statistics

100

%

fixed Fee

£

Contract Value

0

Extras Charged

50

+

Resident Liaisons

%

Reduction on internal resource

3

Months Project Duration
Weeks Project Duration

Carriageway Resurfacing
Weeks Project Duration

£

Bond Reduction

%

Resident Satisfaction
100

Fixed Value

Contract Value

0

Extras Charged

50

Resident Liaisons

reduction on internal resource

3

month project duration

bond reduction

Resident satisfaction

100

%

Fixed fee

0

Extras charged

£

Bond reduction

50

+

Resident liaisons

%

Reduction on internal resource

3

Month project duration

£

Contract value

%

Resident Satisfaction

Client feedback

David Wilson Homes

other Projects

By clicking “Accept”, you agree to the storing of cookies on your device to enhance site navigation, analyze site usage, and assist in our marketing efforts. View our Privacy Policy for more information.